Delivery status AS Monaco · Christmas 2026 Updated 5 November 2026
AS Monaco × Pluro

Christmas 2026: where we are

Eight offers, one launch on 20 November, the day after Fête du Prince. This page shows what still needs to come from the club, where each offer stands, and whether it will be ready for its date. Updated twice a week; last updated 5 November, after our call.

Launch
Friday 20 November, 00:00Monaco time, by schedule
Inputs due
Monday 9 November12 items still open
Runs until
31 DecemberAdvent Calendar to 24 December
The plan

Everything hangs on the club's inputs landing by 9 November. From there it is seven working days to build and test, with acceptance on 18 November.

9 Nov
Club inputs due
9 to 17 Nov
Build and test
19 Nov
Fête du Prince, 19% off
20 Nov
Christmas offers live
24 Dec
Advent Calendar ends
31 Dec
Christmas offers end
01 / This week

What we need from the club

All by Monday 9 November. Each item is a numbered question on the Christmas launch ticket in ClickUp, so an answer there is all that's needed.

01QR tool details and the codes themselves, after the provider meeting on 5 NovemberQR codes ticket, Q1 to Q3Outstanding
02Design for the QR code email, English and FrenchQ2Outstanding
03Advent Calendar product created, link sentQ3Outstanding
04Personalisation products for the Away and Third kitsQ4Outstanding
05Collection links: Christmas gifts, Me & Mini Me, headwearQ5Outstanding
06French copy for all messagesQ6Expected 6 Nov
07Finished banner graphics, desktop and mobile, English and FrenchQ7Outstanding
08T&Cs page linkQ8Outstanding
09Christmas delivery cut-off dateQ9Outstanding
10Yes or no on three decisions: pausing the newsletter pop-up, Black Friday banner order, GA4 only. In-store and the discount app were answered on the call; Q10, Q13 and Q14 are withdrawn.Q15 to Q17Outstanding
11Christmas Box created as a product with 500 units of stock, link sentQ18, new from the callOutstanding
12Black Friday start and end datesBlack Friday ticket, Q1Outstanding
02 / Status

Where each offer stands

Inputs are what we need from the club. Build is where our work is. Status is our honest view of whether the offer will be ready for its date.

Offer Live Club inputs Build Status Note
01Christmas Box and progress bar 20 Nov Outstanding Not started On track Box is now an optional add-on, 500 units; product link needed (Q18). Packing slip question open.
02QR code email 20 Nov Outstanding Not started At risk Needs the QR tool details and codes by 9 Nov. The tightest item in the plan.
03Advent Calendar 20 Nov to 24 Dec Outstanding Not started On track Product to be created by the club
04Train Like a Pro and Double Up & Save 20 Nov Outstanding Not started On track Discount app approved on the call; set-up under way
05Me & Mini Me 20 Nov Outstanding Not started On track Away and Third personalisation products needed
06Training top-up 20 Nov Outstanding Not started On track Cap is optional; the customer picks one if they want it
07Homepage banners and small print 20 Nov Outstanding Not started On track Banners from the club
08Tracking 20 Nov Outstanding Not started On track Not launch critical
09Fête du Prince, 19% off 19 Nov Nothing needed Not started On track Hero banners only; ends the night before the Christmas launch
10Black Friday Dates to confirm Outstanding Not started At risk 25/26 products only. Dates needed now; banners by 18 Nov.
On track: ready for its date At risk: an input or decision is late Blocked: cannot proceed until something changes